The challenge with rear extensions we find, is managing the design to protect the light levels as the building becomes deeper.
Read MoreGoing Underground
Underpinning of the original structure is two thirds done this week. The formwork used is simple but robust, and is moved from stage to stage in line with the sequence advised by the structural engineers.
Read MoreThe Garden Room Starts on Site
Once Party Wall Awards had been issued we were clear for work to start. Initial works have focused on remedial measures to the existing house, such as stiffening the upper floors, tying back internal studs and strengthening external walls at the top of the house, where some weakness had been identified.